Grand Park Canal District – Updated

By Jeff Cheney | On

Update! New Grand Park Housing Information and Potential Dates Released.

Site Development: Phase 1
79 acres of Mixed-Generational Housing
Mass grading will be completed March 14th. City Acceptance November 2014.
Final Release of Utility and pavement plans is pending. Revised plans resubmitted.

Senior Living: Phase 1,  235 Senior Living and 111 Assisted Living/Memory Care Units
Integrated Residential is planning to apply for building permits March 16th. Break ground on site work and utilities mid-June. Commence construction of podium parking and buildings September. Complete construction September 2015

Urban Living: Phase 1, 350 Units
Streetlights Residential is planning to apply for building permits early Summer 2014. Break ground on site work and utilities September.

Cambridge Homes: 45 Garden Homes Start two models and three market homes October

Darling Homes: 46 Garden Homes Start two models and three market homes October

CB Jeni Homes: 58 Town Homes Start One 8 Unit town home building October

Normandy Homes: 41 Manor Homes One model and three market homes October

Drees Homes: 66 Estate Homes One model and three market homes October

Original blog post:
Have you noticed the construction beginning along Legacy Drive near Fire Station #4? This is the first action on a new Frisco mixed-use residential project called the Canals of Grand Park. This innovative development will include single-family homes, patio homes, and some senior living—all incorporated around parks, canals and lots of open space. Click on the rendering to see the full-sized image.